Ethernet Routing Switch 8310 and 8306 chassis installation

Prerequisites

•

Provide adequate space around the unit for access to cable
connectors.

•

Ensure that the surface can safely support the weight of the chassis,
its components, and its attached cables. See

“Chassis installation time

requirements” (page 35)

.

Procedure steps

Step

Action

1

Set the switch on the flat surface and check for proper
ventilation.

Allow at least 2 inches 5.1 cm) on each side for proper
ventilation and 5 inches (12.7 cm) at the front for power cord
clearance.

2

Attach rubber feet to each marked location on the bottom of the
chassis.

The rubber feet are optional but recommended to keep the unit
from slipping.

3

Attach all devices to the ports.

--End--

Procedure job aid: Chassis weight including components

The following table shows the weight of each chassis including the
components.

Chassis

Maximum weight (chassis and components)

8310

225 pounds (lb) (102 kilograms [kg])

8306

140 lb (63 kg)

Mounting the Ethernet Routing Switch 8310 and 8306 chassis in
an equipment rack

Install the Ethernet Routing Switch 8310 and 8306 chassis in a standard
19-inch equipment rack to provide a convenient location for the safe
operation of the switch.

ATTENTION

If you are mounting the chassis in a 23-inch equipment rack, see the rack
manufacturer’s 23-inch-to-19-inch rack adapter installation instructions.

Nortel Ethernet Routing Switch 8300

Installation — Chassis

NN46200-309

01.01

Standard

16 June 2008

Copyright © 2008 Nortel Networks

.

Advertising
Dieses Handbuch ist für die folgenden Produkte bezogen werden: