Start-up

Prerequisites for
commissioning

-

The AC IN cables must be connected to the inverters and in the AC distributor.

-

The inverters must be connected on the DC side.

-

The AC OUT cable must be connected in the AC Combiner and to the public grid.

-

Any existing overvoltage protection must be connected to the inverter.

-

All contact protection devices and covers must be fitted to the inverters and also to the
AC Combiner .

Commissioning

Commissioning of the inverters must only be carried out in line with the inverter installation
instructions and operating instructions.

Carry out AC-side insulation measurement on the AC Combiner
Set up the AC power supply
Check the rotary field

6

-

Insert the fuses

-

Swivel the fuses into place

Close the AC Combiner
Switch on the inverter
Set the required language on the inverter
Set the country setup
Set the date and time
Set the MPP Tracker 2
If overvoltage protection is present:
implement the settings for the overvoltage protection
BASIC menu / Input signal / Ext. Sig. / Triggering method: Warning / Connection type:
N/C
Set the inverter number in the Setup menu under DATCOM
If system monitoring via Fronius Datamanager 2.0 is in place:
run the setup wizard