Ethernet Routing Switch 8310 and 8306 chassis installation

Prerequisites

Provide adequate space around the unit for access to cable
connectors.

Ensure that the surface can safely support the weight of the chassis,
its components, and its attached cables. See

“Chassis installation time

requirements” (page 35)

.

Procedure steps

Step

Action

1

Set the switch on the flat surface and check for proper
ventilation.

Allow at least 2 inches 5.1 cm) on each side for proper
ventilation and 5 inches (12.7 cm) at the front for power cord
clearance.

2

Attach rubber feet to each marked location on the bottom of the
chassis.

The rubber feet are optional but recommended to keep the unit
from slipping.

3

Attach all devices to the ports.

--End--

Procedure job aid: Chassis weight including components

The following table shows the weight of each chassis including the
components.

Chassis

Maximum weight (chassis and components)

8310

225 pounds (lb) (102 kilograms [kg])

8306

140 lb (63 kg)

Mounting the Ethernet Routing Switch 8310 and 8306 chassis in
an equipment rack

Install the Ethernet Routing Switch 8310 and 8306 chassis in a standard
19-inch equipment rack to provide a convenient location for the safe
operation of the switch.

ATTENTION

If you are mounting the chassis in a 23-inch equipment rack, see the rack
manufacturer’s 23-inch-to-19-inch rack adapter installation instructions.

Nortel Ethernet Routing Switch 8300

Installation — Chassis

NN46200-309

01.01

Standard

16 June 2008

Copyright © 2008 Nortel Networks

.

Advertising
Dieses Handbuch ist für die folgenden Produkte bezogen werden: