COMMISSIONING

8.1 General Information

To ensure proper commissioning it should be

carried out by an after-sales service authorized by

the manufacturer. Only then can an extended

warranty period of 3 years in total be granted (cf.

Warranty service).

8.2 Preparation

Prior to commissioning, the following items need to

be checked:

-

All connections of the heat pump must have been

made as described in Chapter 7.

-

The heat source system and the heating circuit

must have been filled and checked.

-

The strainer must have been fitted in the sole

inlet of the heat pump.

-

In the brine and heating circuits all valves that

could impair the proper heating water flow must

be open.

-

The settings of the heat pump controller must be

adapted to the heating installation in accordance

with the instructions contained in the controller's

operating manual.

8.3 Commissioning Procedure

The start-up of the heat pump is effected via the heat

pump controller.

Commissioning of the heat pump

must be performed in accordance with the

mounting and operating manual of the heat

pump controller.

Where an overflow valve is fitted to assure the

minimum heating water flow rate, the valve must be

set in accordance with the requirements of the

heating installation. An incorrect setting may result

in various error symptoms and an increased elec-

tric power consumption. To correctly set the overflow

valve, the following procedure is recommended:

a) Open all heating circuits and close the overflow

valve. Determine the resulting temperature

difference between supply and return flow.

8

b) Close all of the heating circuits that may also be

closed during operation (depending on the type

of heat pump usage) so that the most unfa-

vourable operating state - with respect to the water

flow rate - is achieved.

c) In this operating state open the overflow valve

until approximately the same temperature

difference exists that was measured under a)

when the overflow valve was closed and the

heating circuits open.

Any malfunctions occurring during operation are

displayed on the heat pump controller and can be

corrected as described in the operating manual of

the heat pump controller.

CAUTION!

COMMISSIONING