INSTALLATION OF THE VISUALIZER IN A PLENUM BOX

The Ceiling Visualizer can also be installed in a Plenum box which allows the unit to be turned by +/- 45
degrees. To do this, the mounting plate must be installed in the Plenum box in a centred position.

A non-centred position could later prevent the Visualizer from turning or releasing. A Plenum box
doesn’t allow a horizontal or vertical movement of the Visualizer. Please follow the instructions outlined
on page 7 and page 8 to install the Visualizer in a Plenum box.

DISMANTLE OF THE CEILING VISUALIZER

Should it be required to dismantle the Ceiling Visualizer following relocation or aftersales service,
please follow the instructions outlined below.

Turn off the unit at the main switch and press the release button (fig. 14).
Release the Visualizer to the opened holding position (fig. 15).
Unplug all connected cables and remove them fromt the ceiling mount (fig. 16).
Remove the ceiling mount once all cables are completely removed.

Fig.14

Fig.15

Fig.16

Remove both hex safety screws and stabilization brackets (fig. 17)
Press the safety lever to the top by using a normal slit screw driver (fig. 18) and turn the lever to the
centre position by 60 degrees (the lever must click in pulled position).

The Ceiling Visualizer can not be removed without following this process.

Subsequently, the Visualizer must be moved back towards the ceiling and locked in place. The
Visualizer can now be removed by turning it by 90 degrees.

Please be aware of the weight of the

unit of 13 kilos (29 pounds) when detaching it from the ceiling. The safety lever will automatically
reactivate with the next installation and will secure the Visualizer from detaching itself.

Lock pin

position

7

Abb. 17

Abb. 18