IMP Pumps CV 32, PV 32 Benutzerhandbuch

Seite 15

Advertising
background image

-15-

GB

H) Dismantling of the pump must be implemented according to the following sequence:

- The lock valves on both the pressure and suction sides must be closed.

- The electrical supply must be switched off.

- The medium in the system must be cooled to a temperature that is not dangerous for

work.

- Additional connections to the pipe should be removed.

- The screws between the pump casing and the driving generator should be unscrewed

and the two separated.

- With damage to the pump casing, loosen the screws on the flanges of the piping and

separate the entire pump from the system.

- With excessive corrosion on the connection contacts, apply any anticorrosive agent for

removing rust.

I) When dismantling do not use excessive force, as damage can occur to individual parts.

J) Damage to the mechanical seal is a sign that it should be replaced entirely. During

dismantling care should be taken not to damage the contact patches and seats were the

mechanical seal is fitted.

- If there is damage to parts that are functionally important for the sealing of the

mechanical seal, it is necessary to change them with the original manufacturer’s parts.

Before re-fitting the mechanical seal, all contact surfaces should be cleaned from dirt

and impurities.

- It is necessary to control the installation measurements, as well as the seal

measurements, centreline, and the parallelism between the shaft and the casing.

- The shaft must be treated within the Rmax 5 ľm ( Ra max=0,8 ali N6 ) values, other

surfaces that are important for the incorporation must be treated better than Rz 10 ľm (

Ra max=2,5 ali N7/N8).

- All edges, plates, and part surfaces coming into contact with the mechanical seal must

be smoothened or rounded (e.g. 2mm x 30 degrees by DIN 24960)

- Installation must be implemented in a clean environment and without unnecessary

force, as there is a danger of plastic deformation, cracking, and breakage of the ceramic

material.

- The installation or dismantling sequence of the mechanical seal should be adapted to

the pump construction.

- To reduce friction during installation all plate rubbers that are laid on the shaft should be

moistened with water or alcohol, or they should be covered with silicone grease.

- There are special instructions for storage and handling of elastic materials:

Natural

rubber must not come into contact with mineral based oils and lubricants!

- The stator is not foreseen for plastic deformation as breakage can occur.

- Flat surfaces must not be unclean or soiled with oils, but must be dry, dust free and

carefully installed.

- For the MG variation, the elastic materials should be moistened with water and pushed

circularly onto the shaft.

Oils and lubricants must not be used! Pressure may be

applied only to the edges of the rounds parts. After installing all the parts, it is necessary

to check if the seal has adapted well.

- The regulatory materials do not require maintenance if we know the overlap position.

A forcible circulation of the pump where the seal is installed is necessary with warm

medium to prevent deposits on the single seals in a compressed state.

- All the air in the seal casing for internal use must be carefully bleed out, and the

mechanical seal must be completely submersed in the medium

(there can be no dry

run!).

K) Please contact the manufacturer, distributor, authorised or maintenance service for spare

parts. For your order, please give the pump type, serial number, and the necessary part or

half product for replacement.

Advertising