6 Commissioning, operation
6. Commissioning, operation
The process transmitter should only be commissioned and operated by skilled
personnel.
6.1 Mechanical mounting
6.1.1 Selecting the installation site
The space required is dependent on the design variant of the process transmitter.
The case head is rotatable through 330° and the display and operating unit can be
inserted and oriented in 90° steps. Thus the process transmitter can be adjusted to the
installation site (see figures under chapter 4.1 “Description”).
Select an installation site that has sufficient space for:
■
Carrying out a safe electrical mounting.
■
Being able to use the operating elements following the mounting.
6.1.2 Mounting the process transmitter
CAUTION!
Defective components.
Physical injury and damage to property.
- Only use original parts.
For information on tapped holes and welding sockets, see Technical infor-
mation IN 00.14 at www.wika.com.
1. Clean the sealing faces and threads. Check these for damage.
Rectify any damage before mounting.
2. Seal the process connection as follows and screw in by hand.
Do not cross the threads.
Parallel threads
Seal the sealing face
with flat gaskets,
sealing rings or WIKA profile sealings.
per EN 837
per DIN 3852-E
Tapered threads
Wrap threads with sealing material,
e.g. PTFE tape.
NPT, R and PT